Doing your best and helping other Scrum team members demonstrates which of the following? (Choose the best answer)
The latest changes and updates from the administration for this exam.
Latest Update: Jun 15 2026
All questions are working fine.
Doing your best and helping other Scrum team members demonstrates which of the following? (Choose the best answer)
Peter, a Project Manager, has raised concerns about your Scrum team’s productivity and progress towards the objectives. Which is the best way to respond to Peter’s concerns? (Choose the best answer)
During the implementation of a Sprint Backlog item, there is a disagreement among team members about what work is required to make the item 'done.' Some argue that it is included in the Definition of Done, while others argue that it is not. Steven, the Scrum Master, notices a debate forming and members taking sides. What is the best course of action for Steven? (Choose the best answer)
Select the three pillars of empirical process control. (Choose the best answer)
Steven, a Scrum Master, is approached by the Developers complaining that one of the senior engineers is using too much time during the Daily Scrums to share technical solutions. Which are the best two actions for Steven to take? (Choose the best two answers)
Select all that apply
The Definition of Done will assist the Scrum team in forecasting the amount of work from the Product Backlog that is deemed feasible to meet the "Done" by the end of the Sprint during Sprint Planning. Which two items best describe the meaning of "Done"? (Choose the best two answers)
Select all that apply
Steven, the Scrum Master, notices that one of the Developers is not attending the Daily Scrum. The Scrum team thinks this is fine because they are all in the same area and already have constant communication throughout the day. Which is the best action for Steven to take? (Choose the best answer)
Over the course of several Sprints, the relationship between the Product Owner and the Developers has suffered. The Developers are not happy with the Product Owner for constantly changing the upcoming items of the product. The Product Owner is not happy as well with the Developers for changing the work that needs to be done during the Sprint. What should Steven, the Scrum Master, do? (Choose the best answer)
An organization has 15 Scrum teams with 15 Scrum Masters and 15 Product Owners, so each team has a Product Owner and a Scrum Master. A Scrum team must have a Product Owner and a Scrum Master to work effectively when working on a single product.. (Choose the best answer)
Developers have been complaining about Chris to Steven, the Scrum Master. Chris is the most knowledgeable about the system they're constructing. He frequently criticizes team members' design and architectural decisions, making them feel bad. What are two good ways for Steven to address this problem? (Choose the best two answers)
Select all that apply